Sauble Beach wastewater treatment Servicing

In order to protect the health of the source water, the health of the Lake Huron shoreline and the health and well-being of all people the Town has researched and proposed a Sauble Wastewater Treatment facility. The proposed service area in Sauble Beach is currently serviced by private septic systems, located on small lots alongside private wells. The Town of South Bruce Peninsula received funding through the Building Canada Fund in 2009. Genivar Consultants were the Engineers for the project. This project involves the possibility of constructing a new wastewater collection system for the community of Sauble Beach in Bruce County.

The Town has completed a Class Environmental Assessment - Schedule C (EA), but has elected to re-open the study to further consider an appropriate location for the Wastewater Treatment Plant, the most appropriate type of Wastewater Treatment Plant and the proposed service area.

A Schedule C project has the potential for significant environmental effects and must proceed under the full planning and documentation procedures specified in this Class EA document. Schedule C projects generally include the construction of new facilities and major expansions to existing facilities. If concerns are raised that cannot be resolved, the Part II Order may be invoked.  

Click here to view the Environmental Study Report Documents.

Timeline of Project


January 11, 2011

A draft Environmental Assessment Report has been submitted to Council. Council elected to file the report until such time as Council has had an opportunity to fully understand the information contained in the report and are offered alternatives to the recommended plan. Council intends to revisit the plan no later than August 31, 2011.


October 12, 2010

Comment Sheet from Public Meeting - 1 per property. Please return by November 8, 2010

Information regarding the Town's Annual Repayment limit

 


October 9, 2010

Public Meeting    Session 1 - 10:00AM to 12:00PM

                         Session 2 -  2:00PM to 4:00PM

 Location : Amabel Sauble Community School, 555 Sauble Falls Pkwy


July 28, 2010

We have received lots of comments and appreciate them, please keep them coming in! (By August 3, 2010 please)


July 10, 2010

Public Meeting Session 1 - 10:00AM to 12:00PM

                        Session 2 -  2:00PM to 4:00PM

 Location : Sauble Beach Community Centre on Community Centre Dr

Presentation
Table Handout of Including Costs for options
Proposed Preliminary Preferred Servicing Area - Option 3 map


May 28, 2010

Public Notice sent to Sauble Residents directing them to this website.

Sources of Groundwater Contamination - Environment Canada Website


April 27, 2010

The Class Environmental Assessment is to be re-opened. This will allow the existing design to be evaluated through this process. Further the EA will consider other major alternatives including expanding the sewer collection system. Alternative locations for discharge of the treated effluent, and alternative sites for the wastewater treatment plant may be reviewed.


January 28, 2010

Public Meeting regarding zone change for Wastewater Treatment Plant lands at Town Hall at 5PM

For further information please call Chris LaForest at County of Bruce Planning 519-534-2092


October 10, 2009

Public Meeting at the Sauble Beach Community Centre, 30 Community Centre Drive, at 9:00 am


September 24, 2009

Residents whose properties are included in the project limits are notified, and initial preliminary cost estimates for allocation are included.